FOR IMMEDIATE RELEASE: Contact: John Truscott

September 24, 1997 (517) 335-6397


Governor Engler Announces Early Completion of I-275

Michigan motorists to benefit from reconstruction job completed ahead of schedule

Governor John Engler today announced that the early re-opening of northbound I-275 would occur by tomorrow afternoon -- Sept. 25.

"The reconstruction project on I-275 ran on schedule and ran smoothly considering the amount of work that had to be accomplished," said Governor Engler. "We are very pleased with how quickly the job was completed."

The concrete reconstruction and adjacent asphalt resurfacing projects between Telegraph Road and I-94 are part of a $39.7 million overhaul of 31 miles of I-275, spanning from the I-75 interchange to I-96/M-14 interchanges. The two projects represent nearly $20 million of the $39.7 million total investment in I-275.

The reconstruction process entailed the complete removal and replacement of over nine miles of roadway. The project also included bridge deck resurfacing and the addition of 9.1 miles of both median and outside shoulders.

The Angelo Iafrate Construction Company, in a joint venture with Interstate Highway Construction, bid to complete the project within 85 calendar days. The project was originally estimated to take 149 calendar days. The project was completed 7 days ahead of the expedited schedule.

To minimize the inconvenience of freeway closures to motorists, M*DOT included an incentive/disincentive provision in the reconstruction contract.

Whenever M*DOT embarks on a project on a highly traveled freeway like I-275, customer delay costs are analyzed. These daily customer costs are then built into the contract to provide an incentive to the contractor to complete the project as early as possible. For every day the contractor is delayed in completing the project, $25,000 per day would be assessed in penalty to the contractor and for every day (maximum of 30 days) the project is completed ahead of schedule, the same amount is paid in incentive. This particular incentive/disincentive clause was based on estimates that the freeway closure would cost taxpayers an additional $25,000 per day in extra user costs.

"The staging worked out better than we thought from both motorist convenience and constructability standpoints," said State Transportation Director James R. DeSana. "Considering that this project -- even on an accelerated schedule -- wasn't due to be complete until September 29, MDOT staff and our contractors have demonstrated their strong commitment to serve Michigan residents and the economy," added DeSana.

Congestion from the closure in the surrounding communities was less of a problem than originally anticipated. According to James Caygill, Chief of Police for Huron Township, "There was much less congestion than expected. We did receive some calls, but not to the degree we anticipated."

A significant factor in reducing congestion and confusion was attributed to good planning and extensive community relations and public information. "Communication efforts relaying information helped motorists prepare for the construction and detours and we have received virtually no complaints about the construction," said Marilyn Hunter, department executive for Detroit Metropolitan Airport.