FOR IMMEDIATE RELEASE CONTACT: John Truscott
AUGUST 7, 1998(517)335-6397
Governor John Engler announced today that the total reconstruction of I-75 from Fort
Street to West Grand Boulevard has been completed and is now fully open for traffic. All
eight lanes at this 2.5 mile stretch of I-75, in Southwest Detroit just south of the
Ambassador Bridge, was completed well ahead of schedule as the contractor worked
round-the-clock, seven days a week, for three months.
"This $20 million investment and 30-year long-term fix in Detroit serves as a
critical link to cars and trucks traveling from the U.S. to Canada and other parts of
Michigan," said Governor Engler.
"This project is just another example of our commitment to fix our roads,"
Engler said. The Governor credited passage of the Build Michigan II plan, the
impact of the recently-passed federal transportation bill (TEA-21), and MDOT's continued
reorganization for record level investments in road and bridge repair this year.
In the past few years, the Michigan Department of Transportation has completed several
major projects on the I-75 corridor which have had a direct effect on improving growth and
development in this area.
Freeway reconstruction began on May 4, 1998, and with the accelerated construction
schedule the project was completed in only three months. "Thanks to the hard work and
dedication of MDOT employees and our contractor, this project was completed ahead of
schedule and will benefit thousands of motorists," said State Transportation Director
James DeSana.
The contractor is Dan's Excavating of Shelby Township.
For more detailed information, contact Gary G. Naeyaert, MDOT Communications at
517-335-3084
Motorists can call the 24-hour hotline for up-to-date construction information
1-800-641-MDOT (6368).